Additions to Pine Lake Inn

Building Cost Gross Building Area Completion Date Client
R12 000 000 1 750m2 June 2010 African Sky Hotels

Absolute Farenden Serviced Apartments

Building Cost Gross Building Area Completion Date Client
R12 000 000 2 200m2 February 2010 Seacrest Investments 120

Upgrade and Additions to Ermelo Inn

Building Cost Completion Date Client
R3 000 000 September 2009 African Sky Hotels

New Casino for Polana

Building Cost Gross Building Area Completion Date Client
R50 000 000 5 000m2 added 2006 Hoteis Polana Lda

Holiday Inn Lusaka

Building Cost Project Type Completion Date Client
R15 000 000 Refurbishment of Rooms 2003 Southern Sun

New Casino for Emerald Safari Resort

Building Cost Gross Building Area Completion Date Client
R350 000 000 20 000m2 2001 Emerald Casino

Protea Centurion Lake Hotel

Building Cost Project Type Completion Date Client
R35 000 000 120 Bed Hotel 2001 Krog Family

Virgin Active Faerie Glen

Building Cost Gross Building Area Completion Date Client
R9 000 000 3 500m2 1996 M + T Developments

Restaurants

Fit-out of various restaurants in Menlyn Shopping Centre
Client: Old Mutual Properties